PMP Question related to issue log and risk register

PMP Question related to issue log and risk register You are the Project Manager; a new team member joins your project. He came across a problem during the execution, which document this new team member should refer to?

A. Issue Log
B. Risk Register
C. Work Performance Report
D. Project Charter

The answer is C: An issue is something that is happening and risk is something that might happen. We must figure out how to resolve the issue and move forward. In case of risk, we need to establish mitigation plans. If a new team member joins he should refer to the "Issue Log". The issue log is a project document where all the issues are recorded and tracked. The issues may happen at any time during the project, the issue log is created for the first time as an output of the “Manage and Direct Project Work” process.

Check out the full one on one webinar of PMP aspirant with Mr. Saket Bansal at

Follow us on:

FB:
Linkedin:
Twitter:
Website:

#pmpquestion
#pmppreparation
#pmpexam

pmi,pmp,project management,project management professional,pmp exam,pmp exam tips,pmp exam questions and answers,pmp exam preparation,PMP Question related to issue log and risk register,issue log in pmp,risk register,izenbridge,izenbridge consultancy pvt ltd,izenbridge pmp,saket,bansal,pmi pmp,Where should we register problem in issue log or risk register,pmp webinar,

Post a Comment

0 Comments